After two delays (caused by poor weather) to the work, repairs on Wetherby Road started on 20th June with the worst affected parts of the road (mainly the sections at the side of the carriageway) being tackled. There will be further road closures (weather permitting) for surface dressing on 23rd and 24th June (09:00 – 16:00) which will finish the planned £52,0000 work. Westfield Ward Councillors will continue to take up residents concerns about the need in the long term for full reconstruction of the road (as will be happening later in the year in parts of Gale Lane) due to the amount of heavy lorries which use the road.